Per Tullstedt uploaded the file: NorDigTestplan_ver_3.1_draft003_DW_Tasks 5-9-10–20181213.docx to Test group 5 years, 10 months ago
Input from David Woolgar: Small updates to Tasks 5-3 and 5-10 in attached document.
-
Per Tullstedt uploaded the file: NorDigTestplan_ver_3.1_draft004-JuhaJokiHbbTV_JanMueller_b.docx to Test group 5 years, 10 months ago
Input from Juha Joki: Editorial updates for HbbTV (tasks 9:9, 9:11, 16:xx), some checks for correct references (chapters, table numbers, etc) to Nordig 3.1 spec. All changes highlighted in yellow.
Additional input from Jan Mueller (Dolby): proposed changes on the HbbTV general section. -
Per Tullstedt deleted the file: NorDigTestplan_ver_3.1_draft004-JuhaJokiHbbTV.docx from Test group 5 years, 10 months ago
-
Per Tullstedt uploaded the file: NorDigTestplan_ver_3.1_subtilting_subset_draft002.docx to Test group 5 years, 10 months ago
Input from Kjell Norberg
-
-
-
Peter Moelsted deleted the file: testfil from Test group 5 years, 10 months ago
-
-
Peter Moelsted uploaded the file: NorDigTestplan_ver_3.1_draft004.docx to Test group 5 years, 10 months ago
-
nordigkleo joined the group NorDigT 5 years, 11 months ago
-
Per Tullstedt uploaded the file: NorDigTestplan_ver_3.1_video_subset_ptu_draft002.docx to Test group 5 years, 11 months ago
Per Tullstedt 2nd proposal video tests d002, updated several test cases, video test cases 2-4 still remains.
-
Per Tullstedt uploaded the file: NorDigTestplan_ver_3.1_RF_draft005_Silicon_Labs_FM_06Dec18.docx to Test group 5 years, 11 months ago
Franck Mantel input/update: I just found a typo in test procedure of task 1:9 (-40dBm input level instead of -60dBm). This typo has been corrected in draft005.
-
-
-
Per Tullstedt uploaded the file: NorDigTestPlan_ver_3.1_Audio_draft004_Merged_JG_JR_Task7_14_17_20181130.docx to Test group 5 years, 11 months ago
From Jonas Rödén (dolby) and Jacobo Giralt (Dolby): Audio draft004 for
– Test task 7 (audio) NGA part + HDMI ARC/eARC for AC-3,
– Test task 14 (navigator) audio parts
– Test task 17 (pref setting) audio parts -
Per Tullstedt uploaded the file: NorDigTestplan_ver_3.1_RF_draft004_Silicon_Labs_FM_30Nov18.docx to Test group 5 years, 11 months ago
From Franck Mantel: this FrontEnd draft004 vs draft003:
– adds yellow highlight to modified/new text proposals
– new proposal for Task 3:22.
and as earlier draft004/003 vs draft002 changes are:
– IRD profile DVB-S2X added (part I chapter 6 and part II chapters 1 and satellite test cases)
– DVB-S2X figures added in tasks 1:4, 1:9, 1:11 and 1:14
-…[Read more] -
Per Tullstedt uploaded the file: NorDigTestplan_ver_3.1_video_subset_ptu_draft001.docx to Test group 5 years, 11 months ago
Input from Per Tullstedt, the very first and unmature draft 001 for the video chapter/tasks. Main updated the requirement text parts.
-
Per Tullstedt uploaded the file: NorDigTestplan_ver_3.1_RF_draft003_Silicon_Labs_FM_29Nov18.docx to Test group 5 years, 11 months ago
From Franck Mantel: Based on NorDig Unified 3.1 satellite requirements, this draft003 was John’s draft002 updated with:
– IRD profile DVB-S2X added (part I chapter 6 and part II chapters 1 and satellite test cases)
– DVB-S2X figures added in tasks 1:4, 1:9, 1:11 and 1:14
– Some typos corrected (Task 1:9 Requirement and IRD Profile(s), Task 1:14 w…[Read more] -
-
Per Tullstedt uploaded the file: NorDig_TestPlan_only_AC4_test_cases_20181122.docx to Test group 5 years, 11 months ago
- Load More